ISO 27001 Risk Treatment Plan: What to Include

By Brian Crocker · Published 22 November 2026 · Last reviewed 22 November 2026

A risk treatment plan records, for every risk you are not simply accepting as it stands, what you are going to do about it, who owns it, and by when. It is a distinct document from the risk assessment (which identifies and scores risks) and from the Statement of Applicability (which records which Annex A controls apply). Auditors check that the three exist separately and that they reconcile with each other. This guide covers what belongs in each, the four decisions available for any risk, and a worked example for a 25-person business.

Three documents, one chain

The most common mistake here is merging two of these into one spreadsheet and assuming a Stage 1 auditor will accept it. They usually will not, because each answers a different question.

Document Question it answers Unit of the row
Risk assessment / register What could go wrong, how likely, how bad? A risk
Risk treatment plan What are we doing about it, who, by when? A treatment action
Statement of Applicability Which Annex A controls apply, and why the rest do not? A control

The chain runs one way: a risk is identified and scored, a treatment decision is taken, that decision selects one or more controls, and the Statement of Applicability records those controls as applicable with a justification. A Stage 1 auditor will pick a risk and walk that chain. If a risk has no treatment row, or a treatment row names a control that the SoA marks not applicable, the chain breaks and that is a finding.

Our ISO 27001 risk assessment template covers the first document and the Statement of Applicability guide covers the third. This page is the middle one.

The four decisions

Every risk gets at least one of four treatment decisions, and — as the worked examples below show — sometimes more than one at once. The NCSC — the UK government's own authority on this — states the set plainly in its guidance on the fundamentals and basics of cyber risk: "Risk must be recognised and then managed in some way; classically to either avoid, accept, treat or transfer risk."

Decision What it means What the plan must then record
Treat (mitigate, reduce) Do something that lowers likelihood or impact The controls, the owner, the date, and the residual risk afterwards
Avoid (terminate) Stop doing the thing that creates the risk What you stopped, and when
Transfer Move the consequence to someone else, typically by insurance or contract The instrument, its limits, and what it does not cover
Accept Decide to do nothing further Who took the decision, on what basis, and when it will be revisited

"Accept" is the one that gets recorded badly, and the definition in the NCSC's cyber security risk management framework is the standard to write to: accepting a risk "means making an informed decision to do nothing (or nothing further) to treat, mitigate, modify or reduce an identified risk (either as a raw untreated risk or as a residual risk that remains after some treatment has occurred)."

Two words in that sentence do the work. Informed — the decision has to show what was known when it was taken. Decision — somebody took it. A risk left blank in a register is not an accepted risk; it is an unmanaged one, and an auditor reads the difference immediately.

On documenting all of it, the NCSC is direct: "These and the other analyses and decisions you have made should be appropriately documented to maintain traceability." It also separates the two artefacts the way ISO 27001 does — "a risk register: this communicates and prioritises risks that have been identified to decision makers and other stakeholders" and "a cyber security risk management plan: this sets out how cyber security risks will be managed and describes those controls that will be implemented to treat identified risks". That second description is, in substance, a risk treatment plan.

What goes in each row

Nine columns cover it. More than that and people stop maintaining it.

Column Why it is there
Risk ID Must match the risk assessment exactly. Auditors cross-reference.
Risk summary One line, so the plan is readable without the register open
Inherent risk score Where it started
Treatment decision Treat / avoid / transfer / accept
Annex A control(s) selected The link to the Statement of Applicability
Action to be taken Specific enough that someone else could do it
Owner A named person, not a department
Target date A date, not "Q2"
Residual risk score Where you expect to land, and whether that is acceptable

Two optional columns earn their space in practice: status (open / in progress / complete), and evidence — where the proof lives once the action is done. The second one saves hours at Stage 2, because it turns "find me the evidence for this control" into a file path. Both are in the free ISO 27001 risk treatment plan template, alongside the nine core columns and the three worked examples below.

A worked example

A 25-person software consultancy, three risks from a register of about thirty.

ID Risk Inherent Decision Controls Action Owner Target Residual
R-04 Ex-employee retains access to the code repository after leaving High Treat Access control; identity management Add repo and cloud-console removal to the leaver checklist; run a quarterly access review against the HR leaver list Ops Manager 31 Jan Low
R-11 Laptop lost or stolen in transit, exposing client data Medium Treat + transfer Media handling; asset management; supplier/insurance arrangements Enforce full-disk encryption on all laptops via MDM; confirm cyber insurance covers data-exposure notification costs IT Lead 28 Feb Low
R-19 Sole developer on a legacy client system is unavailable for an extended period Medium Accept — Accepted by the managing director on 14 January: the client contract ends in eight months and cross-training cost exceeds the residual exposure. Review at the next management review or if the contract is extended. Managing Director Review 30 Jun Medium

R-19 is the row worth studying. It accepts a real risk, and it is nonetheless audit-defensible, because it names the person who decided, the reasoning, the date, and the trigger to revisit. Compare that with the same risk left with an empty treatment column — same risk, same exposure, and a nonconformity.

R-11 also shows something the four-option table can obscure: decisions combine. Encrypting the laptop reduces the likelihood of exposure; the insurance transfers part of the consequence that remains. Recording only one of the two understates what you actually did.

How it connects to the Statement of Applicability

Work in this order. Reversing it is the single most common cause of an SoA that cannot be justified.

  1. Assess the risks.
  2. Decide treatment for each.
  3. The treatments select the controls.
  4. Record those controls as applicable in the SoA, with the risk as the justification.
  5. Record every remaining Annex A control as not applicable, with a reason.

Step 5 is not optional and it is the part most often skipped. UKAS's technical bulletin on the ISO/IEC 27001:2022 transition records the scale of it: "Annex A has been aligned with the controls defined in ISO/IEC 27002:2022, which contains 93 controls (11 of which are new) organised in 4 themes." Every one of those 93 needs a line in the SoA, applicable or not.

⚠️ Check which edition your template uses. The 2022 Annex A has 93 controls in 4 themes. Templates and guides built on the 2013 edition use a different structure and different control numbers entirely, and a treatment plan citing those numbers will not reconcile against a current SoA. Our list of Annex A controls uses the current structure.

Keeping it alive

A treatment plan with every target date in the past is worse than no plan, because it is documentary evidence that the system is not being run.

  • Review it at every management review, and record that you did.
  • Close rows properly: action done, evidence referenced, residual score confirmed, status changed.
  • When a target date slips, change the date and note why. A moved date with a reason is management; a silently overdue date is a finding.
  • Re-run the assessment when something material changes — a new system, a new client category, a new supplier with access to your data — not only on an annual cycle.
  • Accepted risks need a review trigger, because an acceptance that was informed two years ago may not be informed now.

The ISO 27001 internal audit is where you find out whether any of this is actually happening, and what to have ready for the certification audit covers how the plan is sampled at Stage 1 and Stage 2.

Practical takeaway checklist

  1. Keep the risk assessment, treatment plan and Statement of Applicability as three separate documents
  2. Assign at least one of four decisions per risk: treat, avoid, transfer, accept
  3. Record combined decisions where you took more than one action
  4. Write "accept" as an informed decision with a named decision-maker, reasoning, date and review trigger
  5. Nine columns; add status and evidence-location if you want two more
  6. Name a person as owner, never a department
  7. Use real dates, not quarters
  8. Let treatment decisions select the controls, then write the SoA — never the reverse
  9. Give all 93 Annex A controls an SoA line, applicable or not
  10. Check your template uses 2022 Annex A numbering
  11. Review the plan at every management review and record that you did

This article is for general informational purposes only and does not constitute legal, regulatory, cyber security or professional compliance advice. The text of ISO/IEC 27001 and ISO/IEC 27002 is not publicly available, so nothing here is a quotation from either standard and no clause is cited as requiring a specific document format; the risk treatment options are quoted from NCSC guidance, and the 93-control figure is UKAS's, stated of ISO/IEC 27002:2022, with which UKAS says Annex A has been aligned. The worked example is illustrative, not a template to adopt unchanged. Verify requirements with your UKAS-accredited certification body, and treat security decisions for your own environment as yours to make.